LAMAS III-IV RUN-OF-RIVER HYDROELECTRIC POWER PLANT

Lamas III-IV Run-of-River Hydroelectric Power Plant

TGT Enerji Üretim ve Ticaret A.Ş.

Lamas III-IV Run-of-River Hydroelectric Power Plant

  • Installed Capacity: 36,4 MW
  • Annual Average Electricity Production: 75 GWh
  • Main Equipment: 2 x 10,8 MW + 2 x 7,4 MW Pelton Turbine (VATech – Indar)
  • Duration of License: 49 years from 2006
  • Commercial Operation Date: 2009
  • Location: Mersin, Turkey

Shareholder Structure

  • GAMA Enerji: 99,95%
  • EÜAŞ: 0,03%
  • Other: 0,02%